Construction Update: 7/21/22

Share:

Construction continues at FCH. Below are a few updates of where things are at:

Pharmacy
– Above-ceiling work is almost complete
– Bathroom tile installation has started

Surgery
– Steel support plates have been installed

Clinic
-Exterior framing is 75% complete

Conference Center
-Steel erection is 50% complete

Clinic Parking Log
-Sampson intends to pour the parking lot this Fall