Construction Updates
FCH Construction Update
The Ambulance/Maintenance Garage is completed! It was held up this past Fall due to a delay in the garage doors – a national supply chain issue. We will begin full use of the building on February 1st with the FCH
Construction Progress at FCH
Construction of walls and roof decking on the external structure continues on the new pre-post op surgical area as well as the new pharmacy area. In a few weeks, the external work will transition to internal finishes. Exciting things are
Construction Continues
FCH is continuing to see progress on our current construction project. Footings have been poured for the medical clinic, site preparation for footings to be poured for the conference center is under way, interior drywall is getting completed for the
Construction Update: 7/21/22
Construction continues at FCH. Below are a few updates of where things are at: Pharmacy– Above-ceiling work is almost complete– Bathroom tile installation has started Surgery– Steel support plates have been installed Clinic-Exterior framing is 75% complete Conference Center-Steel erection